Landfill Closure Morgantown, KY

Project Description

  • 30 acre landfill
  • 4 month project
  • Mass excavation
  • Air/gas collection layers
    • 4,000 feet of air collection pipe
    • 30,000 ton of gravel for air collection layer
  • Landfill lining and cap closure
  • Rock excavation
  • Road relocation
    • 3,000 ton of rip rap
  • Environmental erosion reduction
    • 10,000 ton of rip rap
  • Cast in place concrete and corrugated metal pipe drainage structures
  • Precautions taken for ammonia gas seeping from landfill

Project Details

  • Location: Morgantown, KY