Bank and River Restoration Waynesboro, VA
Project Description
- Installed 1/4 mile cofferdam & dewatering system
- Excavated & transported several thousand tons of impacted soil
- Placed 18,000 SF of HDPE geocell, mixed biochar soil amendment with subgrade fill
- Compacted backfill and re-graded slopes to 2:1
- Installed 14,000 SF of bank stabilization materials i.e. stone toe, coir fabric, anchored tree logs
- Self performed continuous personnel & perimeter air monitoring