White County, IL Landfill Cell Construction
Project Description
- Constructed:
- 10 acre refuse cell
- Retention pond
- 2 – drainage ditches
- 115,000 cubic yards of mass excavation and top soil removal
- 25,000 cubic yards of sand placement / liner cover
- Excavated 25,568 cubic yards to construct a retention pond and associated ditches
- Excavated 30,644 cubic yards to construct drainage ditch around erimeter property
- Relied on off-road trucks complete project instead of scrapers due to excessive rains
- Wet topsoil was pushed off the 10 acres and stockpiled offsite